We were asked to build a bar in 4 days. Seems reasonable, but the design we came up with was slightly extravagant. Anyways, the first night Mike and I modeled the bar in 3d on the computer and asked just about everybody we knew how high to make the top surface of the bar. We even piled boxes on my kitchen table to try and simulate the leaning at each height. Then there was the dilemna of there being 2 bartenders behind the bar. So, we came out with a 2 level 6' x 6' corner bar. Now, only 3 days left.

Go to the wood pile, choose somewhat reasonable boards to put on bar. Use planed wood to build surface. Trim the edge of the top.

Two days to go

Build the framework under the top of the bar. Assemble the top of the bar.

One day to go

Build the framework under the bottom of the bar. Start cutting boards to make the front of bar. Spray bar.

Congratulations, you just built a bar in 3 days instead of 4.